Bioretention basins, commonly referred to as bioretention cells, are widely used throughout North Carolina to manage stormwater runoff while improving water quality. These stormwater control measures (SCMs) temporarily capture runoff and filter it through engineered soil media and vegetation before the water infiltrates into the underlying soil or exits through an underdrain. When designed correctly, bioretention can address both stormwater quantity and pollutant removal while fitting into commercial, residential, institutional, and mixed-use developments.
In North Carolina, however, a bioretention basin is more than a landscaped depression. When it is used to satisfy regulated stormwater requirements, its design must comply with applicable state Minimum Design Criteria (MDC), along with any additional requirements imposed by the permitting authority or local jurisdiction. In our stormwater management and civil engineering work, we consider these requirements early in site planning because drainage area, groundwater conditions, grading, available footprint, and outlet configuration can all affect whether bioretention is practical for a particular development.
The principal state requirements for bioretention cells are established in 15A NCAC 02H .1052. The North Carolina Department of Environmental Quality (NCDEQ) also publishes a Stormwater Design Manual containing technical guidance for implementing the rules. The current manual lists its Bioretention Cell chapter as revised October 18, 2024.
When Is a Bioretention Basin Required in North Carolina?
Not every development project in North Carolina is required to install a bioretention basin specifically. The stormwater requirements that apply depend on factors such as project location, applicable regulatory program, built-upon area, receiving waters, and whether the project qualifies as low- or high-density development.
Under North Carolina’s post-construction program, qualifying low-density projects generally rely on dispersed flow through vegetated areas and minimized channelization rather than structural treatment. High-density projects must meet applicable runoff treatment or volume-match requirements. Under the runoff-treatment approach, stormwater generated by new built-upon area must be treated by a primary SCM. Projects that increase built-upon area and follow either high-density option generally require structural SCMs.
Bioretention is one of the primary SCMs recognized by NCDEQ and can therefore be used where site conditions and project requirements support it. The key is determining the applicable stormwater program first and selecting and sizing the SCM accordingly, rather than assuming a standard basin configuration will satisfy every project.
Required Separation From the Seasonal High Water Table
Subsurface conditions are one of the first issues that should be evaluated when considering bioretention. North Carolina’s MDC requires the lowest point of a bioretention cell to be at least two feet above the seasonal high water table (SHWT).
There is some flexibility where site conditions make two feet of separation difficult to achieve. The separation may be reduced, but not below one foot, when the applicant provides a hydrogeologic evaluation supporting the design.
This requirement can significantly influence grading and SCM selection on sites with shallow groundwater. Evaluating soils and groundwater early helps prevent a situation where the proposed basin location or elevation must be substantially redesigned late in permitting.
Ponding Depth and Stormwater Storage
A bioretention cell needs sufficient storage above its planting surface to temporarily retain the design stormwater volume. North Carolina limits the maximum ponding depth used for the design volume to 12 inches above the planting surface.
Additional depth can be provided when the basin is also being used for peak-flow attenuation. The state rule allows peak attenuation volume to be stored at depths of up to 24 inches above the planting surface. However, the peak attenuation outlet can be no more than 18 inches above the planting surface.
These elevations need to be coordinated carefully with the basin grading, overflow structure and downstream drainage system. Simply creating a deeper depression does not necessarily provide compliant treatment storage because different portions of the basin’s storage can serve different hydraulic purposes.
Underdrains and Internal Water Storage
North Carolina generally requires a bioretention cell to include an underdrain with internal water storage. An exception is available when a soils report demonstrates that the existing in-situ soil has an infiltration rate of at least two inches per hour before the engineered media is initially placed.
Where internal water storage is used, the top of that storage zone must be at least 18 inches below the planting surface. The design allows treated stormwater to remain within the lower portion of the system rather than immediately discharging through the underdrain.

Underdrain details also affect long-term maintenance. North Carolina requires at least one clean-out pipe on every underdrain line, and those clean-outs must be capped. Providing practical access to these components during design can make future inspection and maintenance considerably easier.
Engineered Media Depth and Composition
The engineered media is fundamental to bioretention performance. North Carolina specifies minimum media depths based on vegetation and whether internal water storage is incorporated into the design.
Cells containing trees and shrubs require at least 36 inches of media. A cell without trees or shrubs requires at least 24 inches where there is no internal water storage and at least 30 inches where internal water storage is provided.
The composition of that media is also regulated. The required homogeneous engineered blend is approximately 75 to 85 percent medium-to-coarse washed sand, 8 to 10 percent fines consisting of silt and clay, and 5 to 10 percent organic matter, such as pine bark fines. The rule identifies acceptable standards for the sand component. Mechanical compaction of the media is prohibited because excessive compaction can interfere with the hydraulic characteristics the system depends on.
Phosphorus Requirements and Nutrient-Sensitive Waters
Media selection becomes particularly important when a project is located in a Nutrient Sensitive Waters watershed. North Carolina regulates the phosphorus index, or P-index, of bioretention media to reduce the potential for the media itself to contribute excessive phosphorus.
The P-index cannot exceed 30 in Nutrient Sensitive Waters as defined by state rules. Outside those areas, the maximum P-index is 50.
This requirement illustrates why bioretention media should be treated as an engineered component rather than ordinary landscaping soil. Material composition, nutrient characteristics, drainage behavior, and installation practices all affect whether the completed system performs as intended.
Vegetation, Plant Coverage and Mulch Requirements
Plant selection is not merely an aesthetic decision. For bioretention cells using vegetation other than sod, the planting plan must be designed to achieve at least 75 percent plant coverage within five years after installation. Tree and shrub canopy coverage is limited to a maximum of 50 percent at the five-year point.
When sod is used, North Carolina requires a non-clumping, deep-rooted species. Where vegetation other than sod is installed, triple-shredded hardwood mulch must be used in the portion of the basin that will experience inundation. The required mulch depth is uniformly two to four inches.
Planting plans should therefore account for mature vegetation rather than focusing solely on conditions immediately after construction. Appropriate species selection can also help the basin tolerate alternating periods of inundation and comparatively dry conditions.
Maintenance Is Part of Compliance
A compliant bioretention basin cannot simply be installed and ignored. The state requires the media to be maintained so that water at the planting surface draws down at a rate of at least one inch per hour.
NCDEQ recommends inspecting SCMs at least quarterly and also advises inspection following larger storms exceeding one inch of rainfall over a 24-hour period. Typical bioretention concerns can include sediment accumulation, erosion, damaged vegetation, clogged inlets, mulch displacement, poor drainage and problems with underdrain components.
Maintenance access should consequently be considered during the initial site layout. A basin that technically fits within a constrained corner of a development may still be poorly located if crews cannot reasonably inspect vegetation, reach drainage structures, remove accumulated sediment or service the underdrain system.
General SCM Requirements Still Apply
Meeting the bioretention-specific criteria in 15A NCAC 02H .1052 is only part of the design process. Structural SCMs used for regulated projects must also satisfy the General Minimum Design Criteria contained in 15A NCAC 02H .1050, in addition to the requirements of the applicable stormwater program.
Local requirements can add another layer of review. Depending on the project location, designers may need to coordinate state stormwater requirements with municipal ordinances, watershed-specific rules, drainage standards, floodplain constraints, erosion and sediment control requirements, and other development regulations.
For that reason, successful bioretention design starts with the entire site’s drainage strategy. Contributing drainage areas, runoff calculations, grading, utility conflicts, soils, groundwater, overflow routing, receiving systems and maintenance access all need to work together.
Designing Bioretention for Long-Term Performance
Bioretention is attractive because it can combine stormwater treatment with landscape design while using several pollutant-removal mechanisms. NCDEQ notes that these systems can remove pollutants through processes including infiltration, filtration, sedimentation, adsorption, plant uptake, microbial activity and evapotranspiration.
Those benefits depend on proper design and construction. Incorrect elevations, unsuitable media, excessive compaction, poor vegetation establishment or inadequate maintenance can compromise a system that appeared acceptable on the plans.
For North Carolina projects, the most reliable approach is to evaluate bioretention during the broader stormwater planning process rather than treating it as an isolated feature added after the site layout is complete. Early coordination allows the basin footprint, drainage area, elevations, groundwater separation, storage, media, underdrain and landscaping to be developed as one integrated system. When those elements satisfy the applicable state and local requirements, a bioretention basin can provide durable stormwater treatment while becoming a functional part of the overall site design.